日前,陽江(jiang)(jiang)市環境保(bao)護(hu)局(ju)高新分局(ju)發(fa)布關于陽江(jiang)(jiang)開寶新材(cai)料實業有(you)限公(gong)(gong)司年產(chan)20萬噸(dun)不(bu)銹(xiu)鋼精加工項(xiang)目(mu)環境影響報告表(biao)的(de)受理公(gong)(gong)告。
陽江開寶新材(cai)料實業有(you)限公司(si)年產 20 萬(wan)噸不銹鋼精加工(gong)項目位于陽江市(shi)高新區港口工(gong)業園海(hai)港三(san)橫(heng)路(lu)南邊地塊(kuai),項目總(zong)占地面(mian)積為 66647.22 平方米(mi),總(zong)建筑面(mian)積為 44014 平方米(mi),項目總(zong)投資為 30000 萬(wan),分兩期進行建設。
建設(she)內容包括:高(gao)速分(fen)條生(sheng)(sheng)產(chan)(chan)線(xian)(xian)(xian)(xian)、切邊飛剪(jian)校平(ping)生(sheng)(sheng)產(chan)(chan)線(xian)(xian)(xian)(xian)、高(gao)速切邊整平(ping)飛剪(jian)線(xian)(xian)(xian)(xian)、平(ping)板(ban)磨(mo)(mo)砂(sha)(sha)線(xian)(xian)(xian)(xian)、整卷磨(mo)(mo)砂(sha)(sha)線(xian)(xian)(xian)(xian)、壓花(hua)線(xian)(xian)(xian)(xian)、平(ping)板(ban) 8K 清洗烘干(gan)線(xian)(xian)(xian)(xian)、整卷 8K 清洗烘干(gan)生(sheng)(sheng)產(chan)(chan)線(xian)(xian)(xian)(xian)、磨(mo)(mo)砂(sha)(sha)鈦(tai)金平(ping)板(ban)生(sheng)(sheng)產(chan)(chan)線(xian)(xian)(xian)(xian)、8K 鈦(tai)金平(ping)板(ban)生(sheng)(sheng)產(chan)(chan)線(xian)(xian)(xian)(xian)、熱轉(zhuan)印生(sheng)(sheng)產(chan)(chan)線(xian)(xian)(xian)(xian)、噴(pen)砂(sha)(sha)線(xian)(xian)(xian)(xian)等(deng),一、二期總共年(nian)產(chan)(chan) 2B 平(ping)板(ban) 26000 噸(dun),磨(mo)(mo)砂(sha)(sha)產(chan)(chan)品(pin)(pin)(pin) 51000 噸(dun),轉(zhuan)印產(chan)(chan)品(pin)(pin)(pin) 5000 噸(dun),亂紋產(chan)(chan)品(pin)(pin)(pin) 1500 噸(dun),交叉紋產(chan)(chan)品(pin)(pin)(pin) 1500 噸(dun),8K 產(chan)(chan)品(pin)(pin)(pin)50000 噸(dun),鈦(tai)金產(chan)(chan)品(pin)(pin)(pin) 25000 噸(dun),壓花(hua)產(chan)(chan)品(pin)(pin)(pin) 40000 噸(dun),合計年(nian)產(chan)(chan) 20 萬(wan)噸(dun)不銹(xiu)鋼精加工產(chan)(chan)品(pin)(pin)(pin)。
總工期(qi)(qi)為 1.5 年,分(fen)兩期(qi)(qi)建設,具體(ti)施工安排如下:
2018 年(nian) 8 月(yue)至 2018 年(nian) 12 月(yue)前(qian),為項目前(qian)期(qi)論證和準備階段。
2019 年 6 月,為(wei)項目一期(qi)建設期(qi)。
2019 年(nian) 12 月,為項目二期建設期,2020 年(nian) 6 月底項目全部竣工驗收,并投入使用。